Project schedule:
- 16.10 - presentation of project subjects
- 23.10 - selection of projects
- 30.10 - 20.11 - project consultations
- 27.11, 04.12 - validation of assumptions
- 11.12 - 08.01 - project consultations
- 15.01, 22.01 - poject submission and evaluation
Requirements:
- presence at the consultations
- 27.11, 04.12 - providing of the initial documentation contatining
analysis of the subject, solutions chosen to adopt and expected implementation
environment
- 15.01, 22.01 - providing of the working application, providing of the
final documentation containing, in addition to the previously prepared, the results
of tests, conclusions originating from the implementation phase and technical data